Steel stock unit complete
SMS are happy to announce that the Steel Stock unit is now complete, racking installed and ready to use. The insulated roof will help […]
Assembling on 3rd day sees panelling installed
It is the 3rd day of installing panelling onto the building, and it provides a view of how spacious the interior is becoming. The […]
2nd Day of Assembly
Contractors have been installing the insulated roof on 2nd day of assembly. The roof has an air filled cavity to keep the building temperature […]
End of 1st day of assembling building
Steelwork for building completed before end of 1st day as promised. Tomorrows plan includes the insulated roof being fastened onto framework and possibly panelling […]
Assembly of building steelwork commences.
Monday 27th October 2014, and delivery of steel work for building has been received on site. Contractors Aganto begin erecting steel framework, and […]
Car Park 90% complete.
Over the weekend of 18th & 19th October contractors complete the car park with a layer of tarmac, this is to be finished off […]